Priced to Win, Costed to Fail: Interrogating the Abnormally Low Tender

LGSS Law
Priced to Win, Costed to Fail: Interrogating the Abnormally Low Tender

Photo: public sector procurement evaluation panel reviewing tender pricing documents, via thumbs.dreamstime.com

A price lands 34 per cent below the mean of the field and 18 per cent below the authority's own pre-tender estimate. The evaluation panel now faces what looks like a straightforward choice between saving money and playing safe. It is neither. Under the UK procurement regime there is only one defensible route: understand the price before anyone relies on it, and then decide in writing.

Why the low price is the difficult one

High prices are easy. They are rejected against published criteria, the reasoning is arithmetic, and the audit trail writes itself. A low price invites a different and more dangerous set of assumptions — that the market has been tested, that the authority has secured exceptional value, that a rival bidder's complaint is simply sour grapes.

None of those assumptions survives contact with a delivery failure. The consequences of an unsustainable tender do not appear at award; they appear in year two, when the mobilisation budget has gone, the subcontractor margin has evaporated and the service is being propped up by the client. By then the contractual remedies available are costly, slow and, in the case of a service with a statutory dimension, politically exposed.

What the rules actually ask of you

The current framework, together with its predecessor at regulation 69 of the Public Contracts Regulations 2015, proceeds on a simple logic. A tender that appears abnormally low is not to be accepted or rejected on instinct. It is to be investigated.

In practice that means four steps, in order. First, identify the tender as abnormally low, using whatever method the procurement documents specify — a percentage below the mean, a comparison with the estimate, a comparison with other bids, or a judgement that the price is inconsistent with the specification. Second, seek an explanation in writing, giving the bidder a genuine opportunity to account for the figure. Third, consider that explanation against the actual contract, not against the bidder's confidence. Fourth, decide, and record why.

The legitimate explanations are narrow in number but broad in scope: a genuinely more efficient delivery model, a technical solution the authority had not contemplated, exceptional favourable conditions, or an error in the authority's own estimate. Illegitimate explanations are equally recognisable — a misunderstanding of the specification, a price built on non-compliance with employment or environmental obligations, or an assumption of state support that does not exist.

The boundary that must not be crossed

The explanation stage is an investigation, not a negotiation. Equal treatment means a bidder cannot be invited to improve the offer, restructure the price or add conditions in response to a query. Information asymmetries must be managed: if one bidder is asked to explain a pricing assumption, the record must show why that question was asked and that no advantage was conferred. Queries should be framed to test the price as submitted, not to sketch a better one.

Commercially sensitive detail supplied during the exercise still deserves protection, but confidentiality cannot be used to shut down scrutiny of the figure itself. The authority is entitled to a comprehensible account of how the price is built.

Reading a price for signs of strain

A written explanation will rarely say the thing that matters. What it will do is disclose the assumptions underneath. Look for labour rates set below the National Living Wage after employer costs, or below the real Living Wage where the authority has committed to it. Look for pension contributions that do not reflect the transferring staff's actual scheme, and for TUPE liabilities priced as an afterthought. Look at mobilisation, at subcontractor margins, at indexation that assumes flat prices in an inflating input market, at volume assumptions more ambitious than the authority's own demand modelling, and at risk contingencies set at zero for risks that will certainly crystallise.

In construction and property work, the same tests apply against the pricing document and the programme. In adult social care and grounds maintenance, they apply against the cost of a compliant workforce. In digital services, they apply against the cost of security accreditation and the support model after year one.

Deciding, and deciding defensibly

Acceptance is permissible where the explanation is coherent and the risk is managed rather than wished away. That usually means contractual machinery: a parent company guarantee or performance bond, milestone-linked payment rather than front-loaded sums, price review and indexation clauses that survive scrutiny, key performance indicators with consequences, step-in and termination rights that are actually operable, and a contract management allocation proportionate to the risk.

Rejection is equally permissible, but it must be reasoned, notified and consistent. A bid cannot be rejected simply because it is cheap; genuine economies are a legitimate basis for a competitive advantage. What can be rejected is a price the authority does not understand and cannot tie to a deliverable service.

The decision record should answer, in plain terms: what was asked, what was received, what was tested, what remained unexplained, who took the decision, under which delegation, and on what evidence. Assumptions recorded at award become the standard against which a later challenge — or a later section 114-style reckoning — will be measured.

The question to ask before signing

Strip it back. If this bidder delivers exactly what the contract says, at the price offered, with the margin disclosed, will the service still be there in three years? If the honest answer is that nobody knows, the tender is not a bargain. It is an unquantified liability, and it belongs in the file as such.

All Articles

Related Articles

The Duty Before the Decision: Evidencing Equality Analysis in Commissioning

The Duty Before the Decision: Evidencing Equality Analysis in Commissioning

Sounding Without Steering: Pre-Tender Engagement That Withstands Review

Sounding Without Steering: Pre-Tender Engagement That Withstands Review

Borrowed Time: Proving Extreme Urgency Before You Sign the Direct Award

Borrowed Time: Proving Extreme Urgency Before You Sign the Direct Award